Setup the Sauna Mini

  • Updated

Please read the Safety Precautions and Assembly Warnings and Warranty before setting up the Sauna Mini.

 

Power Requirements

To prepare for your sauna arrival, you’ll need to do the following:

  • Have a licensed electrician install the outlet on a dedicated circuit.
  • Supply a power cord long enough to go from your outlet to your sauna.

 

Location Requirements

sauna_mini_electrical_requirements_1.png

 

Hardware and Tools

Tools 1-1.png

 

What you will need

Tools 2 1-1.png

 

Assembly Sections and Parts

SM_Exploded_White_1transparent.png

Assembly Instructions 

Step 1

  • Prepare a flat, level, and stable (4’4” x 4’9”) surface to set up your sauna. 
  • Position the sauna floor (A) so that the “heater side” is on your right when you are facing the intended location.
_Step 1_1-1.png

Step 2

  • Keep brackets on the door and carefully place the door on it’s side
  • Attach door feet (B) and door header beam (C) to the door
_Step 2_1-1.png

Step 3

  • Using two people carefully pick the door (D) up and place it against the front of the floor (A). 
  • There are pockets in the left and right side of the floor where the bolts will push through.
  • Before pushing the door all the way in, find the door sensor wires at the bottom left of the door and make sure to connect them. 
  • Once the door sensor is connected push the door bolts all the way in and secure with the 2 half moon washers and 2 nuts with the provided socket wrench on each side. 
/!\ Please be careful not to set the door on cement or drop it.
_Step 3_1-1.png

Step 4

  • While someone holds the door up, secure the door with the included 45 degree brace (S) with two screws on the left side to brace it straight up. The door is heavy and will need to be braced before the other walls go in. 
  • Now using the rocks, stack them on the back of the floor to use as a counterweight, so the door doesn’t fall forward.
  • DO NOT open the door until the sauna is fully assembled. (!) Risk of tipping. 
  • You can now unscrew and remove the brackets on the side of the door.
Step 5_1x1.png

Step 5

  • The Huum Uku Controller (H) is located on the right outside of the door. 
  • Remove the black dial on the controller to see the two screws securing it. 
  • Unscrew both screws and remove the Huum Uku Controller (H). 
  • Please set both pieces to the side for later use. 
_Step 4_1-1.png

Step 6

  • Carefully lift the heater panel (E) and place it at a slight angle. You will need a slight gap for the wires to feed through the door post.
  • Before settling it into the space, take the bundle of wires and feed it through the hole where the Huum Uku Controller (H) will be installed on the door.
_Step 6_1-1.png

Step 7

  • Once the wires are fed all the way through, place the heater panel (E) into the groove in the floor (A). 
  • Have one person hold the panel stable and grab the right back post (G).
  • Secure the right back post (G) to the back of the floor (A) using a half moon washer and nut with the socket wrench. 
_Step 7_1-1.png

Step 8

  • Grab the top heater panel beam (F)
  • Secure it to the top of the heater panel (E) using a screw and flat washer with the socket wrench.
  • Then the top angled lag screw and washer goes in to secure the heater panel (E) to the door on the top front.
  • Do not over-tighten and strip the wood.
_Step 8_1-1.png

Step 9

  • Slide the back panel (I) in carefully. 
  • Make sure it is seated completely in the groove in the floor (A) and the back right post (G). 
_Step 9_1-1.png

Step 10

  • Grab the back left post (K). 
  • Secure the back left post (K) to the back of the floor (A) using a half moon washer and nut with the socket wrench. 
_Step 10_1-1.png

Step 11

  • Use the drill to remove the 45 degree brace (S).
_Step 11_1-1.png

Step 12

  • Grab the back top beam (J).
  • Secure it using the lag bolt and flat washer with the socket wrench.
_Step 12_1-1.png

Step 13

  • Place the left panel (L) in carefully. 
  • Please note: you will need two people to lift the panel up and into the section. It should fit in like a puzzle. 
_Step 13_1-1.png

Step 14

  • Find the top left beam (M) and using the 3 screws and flat washers, secure the beam to the top of the panel with the socket wrench.

 

_Step 14_1-1.png

Step 15

  • Grab the roof (N) and slide it onto the top of the sauna from front to back. 
  • The roof has a panel on the bottom that should fit snugly into the top of the sauna to seal it. 
  • Take the roof fasteners (JJ) and secure the roof on the four corners and one screw in the center of the front and back. 
_Step 15_1-1.png

Step 16

  • Connect the wires from each panel where the benches will be placed. 
  • Grab the foot rest (O), holding it vertical, bring it into the sauna.
  • Place the foot rest on the bottom slot and secure it with the bracket below.
  • Bring in the top bench (P) and secure it above the foot rest (O) with the brackets.

 

Step 16-17_1x1.png

Step 17

  • Locate the knee guard (Q).
  • Using 3 screws, secure the knee guard around the heater as pictured
  • Please note: the right side screw will go in at about a 45 degree angle to secure the knee guard to the wall
_Step 18_1-1.png

 

Sauna Stone Preparation

Step 1

  • Rinse the stones with clean water to remove any dust.
Step 1 Stones 1-1.png

Step 2

  • Next, sort the stones by size. The larger stones will be used for the bottom and smaller stones for the top.
Step 2 Stones_1-1.png

Step 3

  • Start by carefully laying the larger stones on the bottom to prevent any from falling out.
Step 3 Stone_1-1.png

Step 4

  • Next, start placing all the other stones in.
  • Finish stacking the stones until the heating elements/coils are no longer visible.
  • Note: This is important for adding water to create steam in the sauna. Water should NOT touch the heating elements/coils, only the stones. 
Step 4 Stones_1-1.png

Installing the Huum Controller

Step 1

  • Grab the Huum Uku Controller
  • Each wire corresponds with a number on the back of the controller. Match the correct wire with the correct number and use a #2 phillips screwdriver to secure each one.
    Yellow #1
    Green #2
    White #3
    Brown #4

Step 2

  • Use the two screws to secure the Huum Uku Controller back onto the wooden mount and then press the dial onto the controller. 
  • Once the controller is installed and both the wires inside of the sauna are connected, then you can plug in the sauna. 
  • Power cord required: NEMA L14-20P to L14-20R power cord
Step 2 Humm 1x1 .png

Step 3

  • Press the controller dial button and hold it for a few seconds until the screen lights up. 
  • Turn the dial up and down to set your desired temperature.
  • To turn on the light and use the vent fan, press the dial button twice quickly. 

 

 

Was this article helpful?